Mumbai: McNally Bharat Engineering Company on Monday said it has bagged an order worth Rs438 crore for commissioning of three plants at power major NTPC’s Bongaigaon Thermal Power Project.
The scope of work includes supply, installation, testing and commissioning of Coal Handling, Lime Handling and Gypsum Handling Plant for Bongaigaon Thermal Power Project (3x250MW), McNally Bharat said in a filing to the Bombay Stock Exchange (BSE).
The contractual period of completion of project is within 30 months, it added.
Shares of McNally Bharat Engineering rose 1.91% and were quoting at Rs262.45 in the afternoon trade on BSE.