Boeing to delay jet deliveries -WSJ

Boeing to delay jet deliveries -WSJ
Comment E-mail Print Share
First Published: Wed, Nov 19 2008. 11 49 AM IST
Updated: Wed, Nov 19 2008. 11 49 AM IST
Bangalore: Plane maker Boeing is reworking its entire production schedule, adding up to 10 weeks to original delivery dates for all 3,734 jetliners in its order backlog as it tries to recover from a machinists’ strike, the Wall Street Journal said, citing people familiar with the situation.
Since early November, Boeing officials have been working to bring production lines back up to speed, after they lay dormant during a 58-day strike by the International Association of Machinists and Aerospace Workers, the paper said.
The process, which calls for careful coordination among hundreds of suppliers and tens of thousands of workers worldwide, could take several weeks, the paper added.
Boeing officials could not immediately be reached for comments.
The company officials have decided against trying to kick the factories into a higher gear to make up the lost ground, fearing such a move might backfire and add to manufacturing woes at the Chicago aerospace company’s jet plants, the Journal said.
Boeing is not expected to publicly discuss details of its new schedule, which will include updated financial guidance and projections of how many airplanes it will deliver this year and next, until early December, the paper added.
Last week, Boeing pushed back the schedule on the cargo version of its 747 jumbo by as much as nine months.
Comment E-mail Print Share
First Published: Wed, Nov 19 2008. 11 49 AM IST
More Topics: Company News | Plane | Boeing | Schedule | Jetliners |