Kolkata Metro: High Court gives nod for resumption of East-West corridor work

Accepting a report by IIT-Madras, the court directed the KMRC, the executing agency for the project, to restart work between Esplanade and Sealdah stations in Bowbazar area of central Kolkata

PTI
Updated11 Feb 2020, 03:57 PM IST
The KMRC moved the court seeking its permission to resume work.
The KMRC moved the court seeking its permission to resume work.(Mint)

The Calcutta High Court on Tuesday allowed the resumption of tunnel-boring work for the city's East-West Metro corridor, which had come to a halt after an aquifer burst in August last year leading to severe ground subsidence and collapse of buildings.

Accepting a report by IIT-Madras, the court directed the Kolkata Metro Rail Corporation (KMRC), the executing agency for the project, to restart work between Esplanade and Sealdah stations in Bowbazar area of central Kolkata, in consultation with the institute.

The division bench comprising Chief Justice TBN Radhakrishnan and Justice Arijit Banerjee had in September ordered the suspension of tunnelling work till further orders.

Three months later, the KMRC, in view of a report prepared by its expert committee, moved the court seeking its permission to resume work.

On a prayer by an NGO to get the expert committee report vetted by an independent agency, the KMRC then requested IIT-Madras to review its findings.

The institute, in its report, stated that tunneling work could be resumed.

Work on the project had come to a halt after a machine boring a tunnel hit an aquifer in Bowbazar on August 31 last year, triggering large-scale subsidence. Many buildings developed cracks and hundreds of people had to be relocated.

However, truncated services between Sector V in Salt Lake to Yuva Bharati Krirangan stadium are scheduled to commence on February 13.

Catch all the Business News, Market News, Breaking News Events and Latest News Updates on Live Mint. Download The Mint News App to get Daily Market Updates.MoreLess
First Published:11 Feb 2020, 03:57 PM IST
HomeNewsIndiaKolkata Metro: High Court gives nod for resumption of East-West corridor work

Most Active Stocks

Tata Steel

166.80
03:59 PM | 15 JUL 2024
-1.9 (-1.13%)

NTPC

385.65
03:58 PM | 15 JUL 2024
8.4 (2.23%)

Bank Of Baroda

258.60
03:53 PM | 15 JUL 2024
7.85 (3.13%)

Bharat Electronics

331.25
03:55 PM | 15 JUL 2024
-2.05 (-0.62%)
More Active Stocks

Market Snapshot

  • Top Gainers
  • Top Losers
  • 52 Week High

Indian Overseas Bank

68.33
03:41 PM | 15 JUL 2024
4.68 (7.35%)

M M T C

94.92
03:40 PM | 15 JUL 2024
6.31 (7.12%)

NLC India

297.75
03:57 PM | 15 JUL 2024
18.6 (6.66%)

IDBI Bank

91.54
03:58 PM | 15 JUL 2024
5.6 (6.52%)
More from Top Gainers

Recommended For You

    More Recommendations

    Gold Prices

    • 24K
    • 22K
    Bangalore
    74,771.00290.00
    Chennai
    73,827.00-145.00
    Delhi
    73,972.00-799.00
    Kolkata
    74,045.0073.00

    Fuel Price

    • Petrol
    • Diesel
    Bangalore
    102.86/L0.00
    Chennai
    100.75/L-0.01
    Kolkata
    104.95/L0.00
    New Delhi
    94.72/L0.00
    OPEN IN APP
    HomeMarketsPremiumInstant LoanMint Shorts