Business News/ News / India/  Mumbai-Ahmedabad bullet train: First visuals released. Take a look
BackBack

Mumbai-Ahmedabad bullet train: First visuals released. Take a look

After the completion of this project, the distance between Mumbai and Ahmedabad will be completed in just 2 hours
  • The total estimated cost of the project is ₹1,08,000 crores
  • The E5 Series ShinkansenPremium
    The E5 Series Shinkansen

    The Japanese embassy has released the first official photos of E5 Series Shinkansen, also known as Japan's Bullet Train, which will be modified for use as rolling stock of the Mumbai-Ahmedabad High-Speed Rail project (MAHSR).

    The MAHSR, also known as the Bullet Train Project, has been sanctioned with a target to be completed by 2023. The project of 508-kilometre length has been sanctioned by the Government.

    After the completion of this project, the distance between Mumbai and Ahmedabad will be completed in just 2 hours. The bullet train will run at an average speed of 320 km per hour with a maximum speed of 350 km per hour.

    It is being executed by a special purpose vehicle namely National High-Speed Rail Corporation Limited (NHSRCL), with financial and technical assistance from the Government of Japan.

    The MAHSR project was sanctioned for implementation with the technical and financial assistance of the Japanese government in December 2015.

    The total estimated cost of the project is 1,08,000 crores.

    L&T contract

    The transportation infrastructure business of L&T Construction, the construction arm of Larsen & Toubro, secured the mega-contract from NHSRCL to construct 87.569 km of the MAHSR in November this year. L&T classifies contracts upwards of 7,000 crore in the mega category.

    The scope of the MAHSR – C6 package includes the construction of viaducts, one station, major river bridges, maintenance depots, and other auxiliary works. This particular package represents 17.2% of the total length, running elevated from the outskirts of Vadodara to the outskirts of Ahmedabad with one station at Anand/Nadiad.

    Land acquisition

    The Railway Board Chairman V K Yadav had said in September that 82% of the land for the bullet train project has been acquired in Gujarat, in Maharashtra land acquisition is only at 23%.

    The total land required for the entire project is 1,380 hectares, where 939.69 hectare falls in Gujarat, 431.2 hectare falls in Maharashtra and 8.70 hectares in Dadra and Nagar Haveli.

    The NHSRCL has envisaged integration of passenger terminals of the bullet train with the Railways and Metro at Sabarmati and Ahmedabad.

    For this integration, various Railway facilities will be required to be shifted. Besides, electrical overhead lines and civic utilities such as water and Drainage pipes, roads, telecom cables and infrastructure will also be required to be shifted to accommodate the bullet train network.

    Unlock a world of Benefits! From insightful newsletters to real-time stock tracking, breaking news and a personalized newsfeed – it's all here, just a click away! Login Now!

    Catch all the Business News, Market News, Breaking News Events and Latest News Updates on Live Mint. Download The Mint News App to get Daily Market Updates.
    More Less
    Published: 19 Dec 2020, 05:30 PM IST